The Union Cabinet gave its nod to investing Rs 12,031 crore for laying transmission lines to evacuate electricity generated from renewable power projects in seven states.
The project, called Green Energy Corridor Phase-II, would involve laying 10,750 circuit kilometres of transmission lines by 2026, Union minister Anurag Thakur told reporters.
The scheme’s total estimated cost is Rs 12,031.33 crore, including Central Financial Assistance (CFA) of 33 per cent of the project cost (about Rs 3970.34 crore).
“The Cabinet Committee on Economic Affairs, chaired by Prime Minister Narendra Modi, today approved the scheme on Green Energy Corridor (GEC) Phase-II for Intra-State Transmission System (InSTS) for the addition of approximately 10,750 circuit kilometres (ckm) of transmission lines and approx. 27,500 Mega Volt-Amperes (MVA) transformation capacity of substations,” an official statement said.
The scheme will facilitate grid integration and power evacuation of about 20 GW of renewable energy (RE) projects in seven states — Gujarat, Himachal Pradesh, Karnataka, Kerala, Rajasthan, Tamil Nadu and Uttar Pradesh.
Thakur said the transmission systems will be created over 5 years during 2021-22 to 2025-26 fiscal years.
The minister added that 80 per cent of the phase one work has been completed. The outlay of the first phase was Rs 10,142 crore.
The statement further said the CFA will help in offsetting the intra-state transmission charges and keep the power costs down. Thus, the government support will ultimately benefit the end-users, it added.
The scheme will help in achieving the target of 450 GW installed RE capacity by 2030.
It will also contribute to the long-term energy security of the country and promote ecologically sustainable growth by reducing the carbon footprint, as per the statement.
Besides, the project will generate large direct and indirect employment opportunities for both skilled and unskilled personnel in power and other related sectors, it said.
This scheme is in addition to GEC Phase-I which is already under implementation in Andhra Pradesh, Gujarat, Himachal Pradesh, Karnataka, Madhya Pradesh, Maharashtra, Rajasthan and Tamil Nadu for grid integration and power evacuation of about 24 GW of RE.
It is expected to be completed this year.
Phase-I is for the addition of 9,700 ckm of transmission lines and 22,600 MVA capacity of substations having estimated cost of transmission projects of Rs 10,141.68 crore, with CFA of Rs 4,056.67 crore.
Source: https://www.outlookindia.com
Tags: CFA, Green energy corridor, Renewable Energy
Recent Posts
Govt urges sugar industry to diversify into green fuels
Cement sector must innovate to achieve net-zero emissions
India’s ethanol production capacity reaches 1,685 crore liters
Sembcorp bags first solar plus energy storage project in India
Wärtsilä to power world’s largest cement carrier for NovaAlgoma
Ethanol sourcing from sugar mills to be less this season
Centre grants approval for 47 ethanol projects in Bihar
China builds seawater hydrogen production project